Sharjah has approved the master plan for a 400MW data centre complex in its communications technology free zone in Kalba, on 285,000 square metres of land on the emirate’s east coast, the government’s media office said on 19 November.
The plan gives Sharjah a defined site, a power plan and a licensing desk for large computing projects. For cloud and AI operators weighing space in the UAE, it adds an east-coast option outside the main Dubai and Abu Dhabi clusters, about three kilometres from the Gulf of Oman.
What the Kalba master plan includes
The plan was approved by Sheikh Dr Sultan bin Ahmed Al Qasimi, Deputy Ruler of Sharjah and chairman of the SCTA, according to Sharjah24, the emirate’s official news service. The complex is designed around a target total capacity of 400MW.
The site covers 285,000 square metres and is split into six plots. The plots can be merged, so a single operator could take a larger campus.
The plan sets aside land for two power stations to supply the data centres. It also reserves sites for telecoms networks, water and other operating services.
A business centre on site will handle company formation and commercial licences. The plan also includes a gateway, office and administrative buildings, open spaces and walkways.
The free zone sits on Kalba Ring Road. The media office said the aim is to attract global companies, investment and specialist talent in technology, AI and data centres.
No investment figure, developer, tenant or construction timetable was announced. News on Projects, which reported the approval on 20 November, also noted that developers, contracts and a completion schedule had not been confirmed.
How the free zone was set up
The Kalba zone is not new. The Ruler of Sharjah, Sheikh Dr Sultan bin Mohammed Al Qasimi, created the Sharjah Communication Technologies Free Zone by Emiri decree in July 2024, Sharjah24 reported at the time. Its English name is COMTECH.
The decree gave the zone its own legal personality and financial and administrative independence, linked to the communications technology authority. Its powers include licensing marine and land cable links and setting up data centres for companies in the zone.
The master plan published this week is the first public layout for the zone in the Sharjah24 reports read for this story.
How 400MW compares
A 400MW target is large by any standard, but it is smaller than the biggest Gulf projects. The UAE has plans for a 5GW AI campus in Abu Dhabi, The National reported on 20 November.
The same report cited JLL estimates that global data centre capacity stands at about 103GW and is likely to reach about 200GW by 2030. It also cited the International Energy Agency (IEA), which put data centres at about 1.5% of global electricity use in 2024, with demand growing about 12% a year.
Power is the constraint that keeps coming up across the region. Reserving land for two dedicated power stations inside the master plan is Sharjah’s answer to that question, although the plan does not say how they will be fuelled or who will build them.
What happens next
The approval covers the master plan only. The media office did not give a date for the first plot allocations, the power stations or the first data centre. The next signals to watch are a named developer or operator for one of the six plots, and details of how the two power stations will be supplied.