The AI data centre plans announced across the Middle East, Africa and South Asia in November have one thing in common: they are being sold on electricity. Sharjah has set aside land for two power stations beside a planned 400MW data centre complex, Saudi Arabia is paying for substations before servers, and South Africa’s president is offering old power station sites with their grid connections. Where power is short or expensive, as in Pakistan, operators are lobbying for cheaper tariffs before they commit. The competition for AI investment in these markets is turning into a competition over megawatts.
Data centre projects now arrive with their own power plans
The clearest example came on 19 November. Sheikh Dr Sultan bin Ahmed Al Qasimi, Deputy Ruler of Sharjah and chairman of the Sharjah Communications Technology Authority, approved the master plan for a communications technology free zone in Kalba, Sharjah24 reported. The 285,000 square metre site includes a data centre complex with a target total capacity of 400MW and dedicated sites for two power stations to serve it. No investment figure or timetable was given.
Saudi Arabia is putting money into the grid first. The National Infrastructure Fund (Infra) and HUMAIN, the kingdom’s AI company, signed two financing agreements worth up to SAR2.5bn ($667m) on 8 November, according to Capacity. Up to SAR1.1bn pays for GPUs, about 25MW of IT load. The larger share, up to SAR1.4bn, pays for substations, transmission lines and grid connections designed for up to 1GW of IT capacity, or 40 times the load being financed now.
“Through these agreements, we aim to unlock investment well beyond Infra’s own commitment,” said Esmail bin Mohammed Alsallom, chief executive of Infra, as quoted by Capacity. HUMAIN targets 3GW of AI data centre capacity by 2030 and more than 6GW by 2034, the same report says.
Both plans put grid capacity ahead of the computing it will serve. In Saudi Arabia, the money for substations and lines is larger than the money for chips.
South Africa offers ageing power station sites
South Africa is making a similar pitch with assets it already has. Speaking in San Jose on 18 November, President Cyril Ramaphosa told an AI investment conference that the country has power station sites approaching the end of their operational lives that may be suitable for redevelopment. Some, he said, already have grid connections, transport links and industrial facilities, and could host data centres with proper planning and investment. He did not name sites.
“We have substantial energy resources, including some of the world’s best solar and wind resources,” Ramaphosa said. He also said the government was expanding generation, strengthening transmission and building a more competitive electricity market.
The offer matters because South Africa’s demand could grow quickly. Data centre capacity could rise from about 400MW to at least 1,200MW, adding some 1,000MW to national electricity demand, Daily Maverick reported in February, citing operators’ plans. Teraco has nearly 190MW of IT load, the same report says.
Where power is scarce or costly, the numbers change
In Egypt, the largest planned project is being designed for export as much as for local use. Project Atlas, a campus in New Borg El Arab developed by Income Egypt for Infrastructure and Investment and Sustainable Infra Capital, has a first phase of 180MW aimed at European AI demand, EnterpriseAM reported. Phase one would cost around $2.15bn for the campus alone, excluding equipment, with financial close targeted for the end of 2027 and service in the fourth quarter of 2028.
At the smaller end, Egyptian firms are renting rather than building. Etisalat Business plans a pay-per-use GPU-as-a-service offer under a memorandum with M Empire and Startup Egypt, Amwal Al Ghad reported, citing a government statement. Goa, in India, made the same choice this week: its new AI policy gives startups and government offices access to around 100 GPUs through national and private partners instead of a state-owned facility.
Pakistan shows what happens when electricity is the problem. The country’s mobile operators, Jazz, Zong, Ufone, Telenor and PTCL, have asked the government to move their network sites and data centres from commercial to industrial electricity tariffs, PhoneWorld reported on 11 November. The operators say commercial tariffs for telecom sites have risen about 197% since 2018 and that roughly $2bn of planned investment over three years, in 5G, fibre and AI-ready Tier III data centres, depends on the change, Business Recorder reported. These are the operators’ own figures. The Prime Minister’s Office has directed a task force to finalise recommendations with the Power and Finance divisions.
Even the Gulf faces limits
Demand is rising fast in the Gulf too. UAE data centre electricity use will double to more than 6 terawatt hours (TWh) by 2030, from 3TWh in 2025, Wood Mackenzie forecast in March. That was about 2% of the country’s 173TWh of demand in 2025.
The consultancy’s concern was less about supply than about how operators buy clean power. Corporate and virtual power purchase agreements are not permitted, and rooftop solar is capped per plot, it said. “The procurement gap is policy, not engineering,” said Nicolas Groues, principal consultant at Wood Mackenzie.
What to watch
- Sharjah’s power stations: who builds the two plants in Kalba, at what capacity, and whether a developer signs for the 400MW complex.
- Pakistan’s tariff decision: whether the task force recommends industrial electricity rates for telecom sites and data centres, and whether the Power and Finance divisions accept the cost.
- Named sites in South Africa: whether the government identifies which ageing power stations are open to data centre developers, and on what terms.